The broad time-path for the new power station is as follows:
| Submit EIS | December 2006 |
| Environmental permit granted | November 2007 |
| Building permit granted | April 2008 |
| Start construction | April 2008 |
| Start construction boiler | January 2010 |
| Start-up operations | 2012 |